Anhui Qingyang projectShanghai Maiyao Engineering Technology Co., LTD., on May 8, 2021, signed a 600 tons per day natural gas Maiz coflow lime kiln with Qingyang Xinyuan Charging Plant. The project broke ground on July 1, 2021, and was completed and delivered to the builder on April 23, 2022.
-
Guizhou Gangli ProjectShanghai Maiyao Engineering Technology Co., Ltd. and Guizhou Gangli Xinmin New Materials Co., Ltd. signed on August 16, 2022, two coal-fired Melz parallel flow regenerative lime kilns with a daily capacity of 600 tons and 800 tons respectively, and one calcium hydroxide production line
-
Inner Mongolia 3D ProjectShanghai Maiyao Engineering Technology Co., Ltd. and Inner Mongolia Sanwei New Materials Co., Ltd. signed two 600 tons per day (calcium carbide gas type) Maiz suspended cylinder lime kilns on April 16, 2022.